Note: eSubscribe notifications will be sent when new projects or any addendums are posted
| Project Name: | Status: | Project# |
| Western Avenue | Bid Date: November 24, 2009 | C03020 |
|
General Work Description: The work to be done consists, in general:
The work to be done consists, in general of installing storm drain system, guard rail and shoulder widening on Western Avenue with associated flagging and traffic control required to construct the work, and such other items or details, not mentioned above, that are required by the Standard Specifications, or these Special Provisions shall be performed, placed, constructed or installed. Sealed bids will be received at the office of the Clerk of the Board of Supervisors, Room 100A, 575 Administration Drive, Santa Rosa, California 95403 on November 24, 2009,, until the hour of 2:00 p.m. (according to the wall clock in the reception area of the office of the Clerk of the Board of Supervisors). They then will be transferred to a predetermined meeting room designated by the Sonoma County Department of Transportation and Public Works where they will be publicly opened and read aloud by the Sonoma County Director of Transportation and Public Works or his designee. The Sonoma County Director of Public Works will review the bids and refer the bids to the Board of Supervisors to consider awarding the project within 30 days of bid opening. |
||
|
||
| Project Name: | Status: | Project# |
| Signalization Sebastopol Road at Burbank Avenue | Bids Under Review | C07009 |
|
Bid Date: November 19, 2009 General Work Description: The work to be done consists, in general: Signalization of the intersection of Sebastopol Road at Burbank Avenue; curb ramp reconstruction. Sealed bids will be received at the office of the Clerk of the Board of Supervisors, Room 100A, 575 Administration Drive, Santa Rosa, California 95403 on November 19, 2009, until the hour of 2:00 p.m. (according to the wall clock in the reception area of the office of the Clerk of the Board of Supervisors). They then will be transferred to a predetermined meeting room designated by the Sonoma County Department of Transportation and Public Works where they will be publicly opened and read aloud by the Sonoma County Director of Transportation and Public Works or his designee. Said bids will be referred to the Sonoma County Board of Supervisors for consideration at their next regularly scheduled meeting, on or before December 8, 2009. |
||
|
||
| Project Name: | Status: | Project# |
| Penngrove Sidewalk Improvements | Under Construction | C04012 |
|
Bid Date: September 16, 2009 General Work Description: The work to be done consists, in general: The work to be done consists, in general of pedestrian facility improvements along the west side of Main Street in the town of Penngrove from the intersection of Old Redwood Highway to the intersection with Adobe Road. Curb, gutter, and sidewalk will be installed on the westerly side of the road where it does not currently exist. Where possible, ten foot wide sidewalks will be installed adjacent to existing store fronts, with five foot wide sidewalks elsewhere. Existing sidewalk and curb ramps will be modified to meet current Americans with Disabilities Act (ADA) standards. Utility facilities will be relocated or adjusted, and such other items or details, not mentioned above, that are required by the Standard Specifications, or the Special Provisions shall be performed, placed, constructed or installed. Sealed bids will be received at the office of the Clerk of the Board of Supervisors, Room 100A, 575 Administration Drive, Santa Rosa, California 95403 on September 16, 2009,, until the hour of 2:00 p.m. (according to the wall clock in the reception area of the office of the Clerk of the Board of Supervisors). They then will be transferred to a predetermined meeting room designated by the Sonoma County Department of Transportation and Public Works where they will be publicly opened and read aloud by the Sonoma County Director of Transportation and Public Works or his designee. The Board of Supervisors has authorized the Director of Transportation and Public Works to award the project. The Sonoma County Director of Public Works will review the bids and consider awarding the project within 30 days of bid opening. |
||
|
||
| Project Name: | Status: | Project# |
| Roadway & Bridge Surface Preservation Program | Awarded | M09000 |
|
Bid Date: August 26, 2009 General Work Description: The work to be done consists, in general: Roadway: The work to be done consists, in general of placement of polymer modified asphalt rubber chip seal, on various County Roads together with associated flagging and traffic control required to construct the work, and such other items or details, not mentioned above, that are required by the Standard Specifications, or these Special Provisions shall be performed, placed, constructed or installed. Bridge: The work to be done consists, in general of cleaning expansion joints and replacing joint seals, cleaning bridge decks, treating bridge decks with methacrylate resin, repairing spalled concrete, and removing remnants of an original epoxy overlay at various locations, and such other items or details, not mentioned above, that are required by the Standard Specifications, or these Special Provisions shall be performed, placed, constructed or installed. Sealed bids will be received at the office of the Clerk of the Board of Supervisors, Room 100A, 575 Administration Drive, Santa Rosa, California 95403 on |
||
|
||
| Project Name: | Status: | Project# |
| 2008 Pavement Preservation Program Asphalt Rubber Chip Seal, Various County Roads | Under Construction | C08000 |
| Bid Date: July 1, 2009 Brief Description: The work to be done consists, in general, of placement of polymer modified asphalt rubber chip seal, and slurry seal on various County Roads together with associated flagging and traffic control required to construct the work, and such other items or details, not mentioned above, that are required by the Standard Specifications, or these Special Provisions shall be performed, placed, constructed or installed. Sealed bids will be received at the office of the Clerk of the Board of Supervisors, Room 100A, 575 Administration Drive, Santa Rosa, California 95403 on July 1, 2009, until the hour of 1:00 p.m. (according to the wall clock in the reception area of the office of the Clerk of the Board of Supervisors). They then will be transferred to a predetermined meeting room designated by the Sonoma County Department of Transportation and Public Works where they will be publicly opened and read aloud by the Sonoma County Director of Transportation and Public Works or his designee. The Board of Supervisors has authorized the Director of Transportation and Public Works to award the project. The Sonoma County Director of Public Works will review the bids and consider awarding the project within 30 days of bid opening. Technical questions should be faxed to Steve Urbanek, P.E. at the Department of Transportation and Public Works, FAX: (707) 565-2620. Only faxed requests will receive a response. |
||
|
||
| Project Name: | Status: | Project# |
| Fulton Road Sidewalk Project | Project Complete | C03400 |
| Bid Date:May 13, 2009 Brief Description:The work to be done consists, in general, of roadway reconstruction; installation of new sidewalk, curb and gutter, and curb ramps; and related drainage improvements, and such other items or details, not mentioned above, that are required by the Standard Specifications, or these Special Provisions shall be performed, placed, constructed or installed. Sealed bids will be received at the office of the Clerk of the Board of Supervisors, Room 100A, 575 Administration Drive, Santa Rosa, California 95403 on May 13, 2009, until the hour of 2:00 p.m. (according to the wall clock in the reception area of the office of the Clerk of the Board of Supervisors). They then will be transferred to a predetermined meeting room designated by the Sonoma County Department of Transportation and Public Works where they will be publicly opened and read aloud by the Sonoma County Director of Transportation and Public Works or his designee. The Board of Supervisors has authorized the Director of Transportation and Public Works to award the project. The Sonoma County Director of Public Works will review the bids and consider awarding the project within 30 days of bid opening. Technical questions should be faxed to Levi Gurule, P.E. at the Department of Transportation and Public Works, FAX: (707) 565-2620. Only faxed requests will receive a response. |
||
|
||
| Project Name: | Status: | Project# |
| River Road Slide Repair | Under Construction | C07006 |
| Bid Date: January 12, 2009 Brief Description:The work to be done consists, in general, of a slide repair and road restoration. Sealed bids will be received at the office of the Clerk of the Board of Supervisors, Room 100A, 575 Administration Drive, Santa Rosa, California 95403 on January 12, 2009, until the hour of 2:00 p.m. (according to the wall clock in the reception area of the office of the Clerk of the Board of Supervisors). They then will be transferred to a predetermined location where they will be publicly opened and read aloud by the Sonoma County Director of Transportation and Public Works or his designee. The Board of Supervisors has authorized the Director of Transportation and Public Works to award the project. The Director will review the bids and consider awarding the project within 60 days of bid opening. Technical questions should be faxed to Jack Cunningham at the Department of Transportation and Public Works, FAX: (707) 565-2620. Only faxed requests will receive a response. |
||
|
||
| Project Name: | Status: | Project# |
| State Route 12 Corridor Improvement Project Phase II, Stage 1 | Under Construction | C03401 |
| Bids Date : September 30, 2008 at 2 PM Brief Description:Construction of shoulder widening, curb, gutter and sidewalk and pedestrian lighting, traffic striping and traffic signals and other improvements as shown on the plans. Sealed bids will be received at the office of the Clerk of the Board of Supervisors, Room 100A, 575 Administration Drive, Santa Rosa, California 95403 on September 30, 2008, until the hour of 2:00 p.m. (according to the wall clock in the reception area of the office of the Clerk of the Board of Supervisors). They then will be transferred to a predetermined meeting room designated by the Sonoma County Department of Transportation and Public Works where they will be publicly opened and read aloud by the Sonoma County Director of Transportation and Public Works or his designee. Said bids will be referred to the Director of Transportation and Public Works consideration for award, on or before December 30, 2008.Technical questions should be faxed to Rex Cummins or Janice Thompson at the Department of Transportation and Public Works, FAX: (707) 565-2620. Only faxed requests will receive a response. |
||
|
||
| Project Name: | Status: | Project# |
| Sonoma Mountain Road Slide Repair | Construction Complete | C07002 |
Bid Date: |
||
|
||
| Project Name: | Status: | Project# |
| Geyserville Park & Ride/Visitor Plaza | Construction Complete | W07077 |
Bid Date: April 17, 2008 at 2:00 p.m. Technical questions should be faxed to Bryan Albee, at the Sonoma County Transit, FAX: (707) 585-7713. Responsibility to confirm County possessing Bidder's written question rests with the Bidder. Only faxed requests will receive a response. |
||
|
||