Bid Results
FOR CONSTRUCTION OF
CENTRAL LANDFILL SITE
POWER PLANT EXPANSION
PHASE III
COUNTY PROJECT NO. W06990
|
BID DATE & TIME |
April
25, 2002 at 3:00 p.m. |
|
CONTRACT |
Central
Landfill Site - Power Plant Expansion Phase 3
|
|
ENGINEERS
ESTIMATE |
$244,000.00 |
| PROJECT
NO. |
W06990 |
|
RANK |
BIDDER |
AMOUNT |
|
1 |
Bamer
Construction |
$251,354.60 |
2 |
Schram
Construction |
$259,712.60 |
3 |
Dennis
J. Amorosa |
$299,230.50 |
LOW
BIDDER'S SUBCONSTRACTORS |
| |
|
|
| |
|
|
| |
|
|
|