UST Installations:

All newly installed underground storage tanks must be double walled with the capability of monitoring the interstitial space. The piping must also provide double containment, which includes a line leak detection system, and be able to monitor the entire secondary containment system. ust installation

The following information must be submitted for the installation of UST(s):

  1. County Permit Application.
  2. Two copies of the installation plans (blueprints).
  3. A cut sheet indicating the items to be installed along with a UL type approval.
  4. State Form A and State Form B (a separate Form B is required for each tank).
  5. Site Safety Plan
  6. Monitoring Plan.
  7. Response Plan.
  8. Appropriate fee.
  9. Certificate of Financial Responsibility.
  10. Any other documentation requested by the Department of Emergency Services.